Emerging Trends in Shortened Statutes of Limitations and Statutes of Repose
January 02, 2024 —
Ivette Kincaid & Thomas McCarrick - Kahana FeldIntroduction
A growing trend in construction defect legislation around the country has seen the shortening of statutes of limitation and statutes of repose for a plaintiff to bring claims related to construction defects. Over the past ten years, several states, notably Florida and Texas, have shortened their statutes of repose. This is generally positive news for developers and contractors; however, the specifics and ramifications of these legislative and judicial updates are still unknown.
Statute of Limitations
A statute of limitations sets forth the time that a plaintiff has to sue or allege a particular cause of action against a defendant. These time limitations are codified into law and vary depending on the State and the cause of action. A statute of limitations starts at the occurrence of an injury or damage or at the time the injury or damage is discovered. The statute of limitations may be subject to some exceptions such as tolling for reasons such as the injured party being a minor in which case depending on the particular statute, the statute does not begin to run until after the minor reaches the age of majority.
Reprinted courtesy of
Ivette Kincaid, Kahana Feld and
Thomas McCarrick, Kahana Feld
Ms. Kincaid may be contacted at ikincaid@kahanafeld.com
Mr. McCarrick may be contacted at tmccarrick@kahanafeld.com
Read the full story...
Insurer's Bad Faith is Actionable Tort for Purposes of Choice of Law Analysis
January 08, 2024 —
Janeen M. Thomas - Saxe Doernberger & Vita, P.C.When an insurer handles a claim in violation of its duty to act in good faith, policyholders are often eager to sue the insurer for bad faith, seeking extra contractual damages. Before filing suit, however, it is critical that policyholders consider what state’s law applies to the bad faith claim.
In the recent case of Scott Fetzer Co. v. Am. Home Assurance Co., Inc.1, the Ohio Supreme Court held that Restatement (Second), Conflict of Laws, § 145 (“Section 145"), governed the choice of law dispute, which meant that the insured would be able to obtain discovery of Travelers’ claims-handling procedures, guidelines, internal documents, and communications relating to the claim.2 The insured, Scott Fetzer, argued that the materials were discoverable because documents evidencing an insurer’s bad faith are not protected by attorney-client privilege in Ohio. In response, Travelers argued that the laws of either Indiana (the place where the parties entered into the insurance contract), or Michigan (the location of the insured risk) governed the discovery dispute because Restatement (Second) § 193 (“Section 193”) governs the choice of law analysis for claims that “arise out of insurance contracts.”3 The laws of either Indiana or Michigan were more favorable for Travelers because Indiana does not allow discovery of materials covered by attorney-client privilege, and Michigan does not even recognize a cause of action for bad faith.
Read the full story...Reprinted courtesy of
Janeen M. Thomas, Saxe Doernberger & Vita, P.C.Mr. Thomas may be contacted at
JThomas@sdvlaw.com
NY Project Produces America's First Utility Scale Wind Power
December 23, 2023 —
Debra K. Rubin - Engineering News-RecordDespite financial gyrations in the U.S. offshore wind energy market that have caused project delays and cancellations over the past two years, America now has joined other world nations in having energy generated for the first time from a utility-scale facility.
Reprinted courtesy of
Debra K. Rubin, Engineering News-Record
Ms. Rubin may be contacted at rubind@enr.com
Read the full story...
Labor Shortages In Construction
December 04, 2023 —
Jason Feld & Chris Bates - Kahana FeldSimilar to other industries, the ongoing labor shortage crisis in the United States is detrimentally impacting construction activities in both the residential and commercial sector. According to the Bureau of Labor Statistics, the turnover rate for the construction industry since 2021 has risen to 56%. And while the national unemployment rate ranges between 0.4% to 7.5%, the unemployment rate for construction is roughly four times the national average (See, Associated Builders and Contractors, Markenstein Advisors Report dated July 28, 2023). 73% of workers preferred to stay in a remote work environment, and another 40% of the global workforce has elected to voluntarily remove themselves from the workplace. (See, 2021 Microsoft Work Index). In particular with the construction industry, employment rates have returned to pre-pandemic levels hovering around 12% unemployment in 2020 to 6% in 2022. (See, Joint Center for Housing Studies at Harvard University, Carlos Martin).
So where did all the workers go? During the height of the 2020 Covid-19 Pandemic and for the next few years, the county experienced what most people are calling “The Great Resignation”. May people took jobs with better pay and better alignment with their values. Approximately 40% stated a new business. Many elected to become stay-at-home parents forgoing a paycheck to raise their families while the other spouse works, especially due to the rising costs of childcare. About 1 in every 4 baby-boomers retired. Others took part-time employment, entered military service or left the workforce due to disability or injury. (See, Bloomberg Businessweek).
Reprinted courtesy of
Jason Feld, Kahana Feld and
Chris Bates, Kahana Feld
Mr. Feld may be contacted at jfeld@kahanafeld.com
Mr. Bates may be contacted at cbates@kahanafeld.com
Read the full story...
Insurer Has Duty to Defend Faulty Workmanship Claim
January 22, 2024 —
Tred R. Eyerly - Insurance Law HawaiiThe magistrate judge recommended a determination that the insurer owed a defense to the subcontractor sued for faulty workmanship. Hanover Lloyds Ins Co. v. Donegal Mut. Ins. Co., 2023 U.S. Dist. LEXIS 180877 (W.D. Texas Oct. 5, 2023).
Poe Investments, Ltd. entered into an agreement with Jordan Foster Construction, LLC for construction of an auto sales and service facility ("Facility"). Jordan hired multiple subcontractors, including Texas Electrical Contractors, LLC ("TEC"). Subsequently, Poe sold the Facility to 6330 Montana, LLC ("Montana").
Montana filed suit against Jordan for breach of express warranties, breach of contract, and negligence. Jordon filed a third-party complaint against its subcontractors, including TEC. Jordan alleged that TEC provided "defective and negligent construction work" while carrying out the provision and installation of electrical and fire alarm systems at the Facility.
Read the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Real Estate & Construction News Roundup (1/30/24) – Life Science Construction to Increase, Overall Homeownership Is Majority Female, and Senators Urge Fed Chair to Lower Interest Rates
February 26, 2024 —
Pillsbury's Construction & Real Estate Law Team - Gravel2Gavel Construction & Real Estate Law BlogIn our latest roundup, hospitality and real estate companies create living options, SEC questions some financial institutions on exposure to risks from CRE, renting shows signs of overtaking buying in the housing market, and more!
Read the full story...Reprinted courtesy of
Pillsbury's Construction & Real Estate Law Team
Court of Appeals Upholds Default Judgment: Serves as Reminder to Respond to Lawsuits in a Timely Manner
October 02, 2023 —
Anna Basnaw - Ahlers Cressman & Sleight PLLCIn
Cyrus Way Partners, LLC. (“Cyrus”) v. Cadman, Inc. (“Cadman”), the primary issue on appeal was whether the trial court erred in denying Cadman’s motion to vacate the default judgment under Civil Rules 55 and 60. A default judgment is a legal ruling that can be entered in favor of the plaintiff when the defendant fails to respond to a lawsuit. If that happens, the court may resolve the lawsuit without hearing from the other side. In Washington, a party typically has 20 days to appear in a suit before being at risk for default judgment. If a default judgment is entered for the plaintiff, the defendant can move to vacate the default judgment, meaning the defendant hopes the court will set aside the default judgment as if it never happened. In this case, Cadman, the defendant, presents several ultimately unsuccessful arguments for why the default judgment in favor of Cyrus, the plaintiff, should be vacated.
Cyrus and Orca Beverage Inc. (“Orca”) are under common ownership. In 2018, Cyrus began a project to build a warehouse for Orca, which included the construction of a large concrete slab. Cadman was hired to supply the concrete. Cyrus hired Olympic Concrete Finishing Inc. (“Olympic”) to finish the concrete. On April 1, 2018, Cadman poured the concrete, and Olympic finished the slab. The next day, Cyrus noticed several problems with the slab, which experts hired by both Cyrus and Cadman opined were caused by an abnormally high air content in the concrete.
Read the full story...Reprinted courtesy of
Ahlers Cressman & Sleight PLLC
Denial of Motion to Dissolve Lis Pendens Does Not Automatically Create Basis for Certiorari Relief
November 16, 2023 —
David Adelstein - Florida Construction Legal UpdatesA recent appellate decision out of Florida’s Sixth District Court of Appeal holds that a trial court’s denial of motion to dissolve a lis pendens does NOT automatically give a basis for a petition for a writ of certiorari. Generalized allegations of “irreparable harm” to support the basis for the petition for writ of certiorari are insufficient. Rather, the party moving for the petition MUST clearly demonstrate the irreparable harm; otherwise, the petition for writ of certiorari will fail.
A lis pendens has legal significance. It is a recorded document that notifies the world that there is a pending lawsuit dealing with the real property at issue. This is important because who wants to buy a piece of property that is subject to litigation – that would be a risky transaction!
In CPPB, LLC v. Taurus Apopka City Center, LLC, 48 Fla.L.Weekly D1837a (Fla. 6th DCA 2023), a dispute arose as to a real estate transaction. The owner sold a parcel to a buyer. The owner also owned three adjacent parcels. As part of the transaction, the buyer agreed to perform certain improvements to all of the parcels including those adjacent parcels owned by the owner. The owner deposited funds in escrow for purposes of its share of the improvements. A payment dispute arose regarding the improvements and the buyer sued the seller. The seller filed a counterclaim to rescind the transaction along with a recorded lis pendens on the parcel purchased by the buyer. The buyer moved to dissolve the lis pendens which the trial court denied. This prompted the appeal – a petition for a write of certiorari based on the trial court’s denial of the motion to dissolve the lis pendens.
Read the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com