Expanded Virginia Court of Appeals Leads to Policyholder Relief
January 29, 2024 —
Michael S. Levine & Olivia G. Bushman - Hunton Insurance Recovery BlogExercising its newly expanded jurisdiction that now permits Virginia’s intermediate appellate courts to hear insurance coverage disputes, the Court of Appeals recently reversed a lower court decision that allowed a two-year “Suits Against Us” provision to serve as a basis for an insurer’s refusal to reimburse repair and replacement costs incurred more than two years after the date of loss. Bowman II v. State Farm Fire and Casualty Co., Record No. 1256-22-3 (Nov. 21, 2023). CAV (unpublished opinion).
In the proceeding below, the circuit court found no justiciable controversy and dismissed the complaint where repairs to the policyholder’s fire-damaged home continued more than two years after the date of the fire. The circuit court relied on a two-year limitation in the policy that governed the period within which the policyholder must bring suit against the insurer.
Reprinted courtesy of
Michael S. Levine, Hunton Andrews Kurth and
Olivia G. Bushman, Hunton Andrews Kurth
Mr. Levine may be contacted at mlevine@HuntonAK.com
Ms. Bushman may be contacted at obushman@HuntonAK.com
Read the full story...
Compliance Doesn’t Pay: Compliance Evidence Inadmissible in Strict Liability Actions
February 05, 2024 —
Kyle Rice - The Subrogation StrategistIn Sullivan v. Werner Co., No. 18 EAP 2022, 2023 Pa. LEXIS 1715 (Dec. 22, 2023), the Supreme Court of Pennsylvania (Supreme Court) clarified that in light of its decision in Tincher v. Omega Flex, Inc., 628 Pa. 296 (2014), evidence that a product complied with industry standards is inadmissible in an action involving strict product liability.
In Tincher, the Supreme Court overruled prior case law and reaffirmed that Pennsylvania is a Second Restatement Jurisdiction. As stated in Sullivan, discussing Tincher, under the Restatement (Second) of Torts § 402A, a “seller of a product has a duty to provide a product that is free from ‘a defective condition unreasonably dangerous to the consumer or [the consumer’s] property.’ To prove breach of this duty, a ‘plaintiff must prove that a seller (manufacturer or distributor) placed on the market a product in a “defective condition.””
Read the full story...Reprinted courtesy of
Kyle Rice, White and WilliamsMr. Rice may be contacted at
ricek@whiteandwilliams.com
The Future of Construction Work with Mark Ehrlich
February 19, 2024 —
Aarni Heiskanen - AEC BusinessIn this episode of the AEC Business
podcast, I had the pleasure of speaking with Mark Ehrlich, a veteran of the construction industry from the USA and the author of “The Way We Build: Restoring Dignity to Construction Work.” Our conversation delved into the evolving landscape of construction work and the challenges faced by construction workers today.
Mark shared his extensive background, starting as a carpenter and rising through the ranks to become the head of a 25,000-member union organization. His experience spans decades, and he has authored three books and numerous articles on labor issues.
The historical labor shifts
We discussed the historical shift from a predominantly unionized construction workforce to the current bifurcated system in the US, where union strongholds in the north contrast sharply with the non-union, lower-wage environments in the south and other regions. Mark highlighted the issues of wage theft, declining safety standards, and the exploitation of undocumented workers.
Read the full story...Reprinted courtesy of
Aarni Heiskanen, AEC BusinessMr. Heiskanen may be contacted at
aec-business@aepartners.fi
Real Estate & Construction News Roundup (3/20/24) – Construction Backlog Falls, National Association of Realtors Settle Litigation, and Commercial Real Estate Market’s Effect on City Cuts
April 15, 2024 —
Pillsbury's Construction & Real Estate Law Team - Gravel2Gavel Construction & Real Estate Law BlogIn our latest roundup, bad loans outweigh loss reserves at top six U.S. banks, the FCC announces a proposed rule aimed at “bulk billing,” office-to-multifamily conversion projects grow in major metro cities, and more!
- The National Association of Realtors has agreed to settle litigation that accused them of artificially inflating real estate commissions – a major decision that could reshape the housing market for buyers, sellers and agents. (Rachel Siegel, The Washington Post)
- An NYU professor considers the positives and negatives of cities cutting services or raising other kinds of taxes to offset the continued faltering of the commercial real estate market. (Alan Rappeport, The New York Times)
- Construction backlog fell in February for every size of contractor except for those with under $30 million in annual revenue, while, over the past year, the largest contractors – those with greater than $50 million in revenue – have experienced the greatest decline in backlog. (Sebastian Obando, Construction Dive).
Read the full story...Reprinted courtesy of
Pillsbury's Construction & Real Estate Law Team
John Paulson’s $1 Billion Caribbean Empire Faces Betrayal
November 27, 2023 —
Jim Wyss & Tom Maloney - BloombergIn the decade since hedge fund billionaire John Paulson took a grand gamble on Puerto Rico, he’s faced the wrath of the markets and mother nature.
He’s navigated hurricanes, earthquakes, the pandemic and the largest municipal bankruptcy in US history to amass a portfolio of luxury hotels and resorts, high-end office blocks, and auto dealerships catering to the island’s rich.
Now, just a few months after breaking ground on one of San Juan’s tallest and most exclusive residential towers, Paulson is facing a new wave of threats: lawsuits that strike at the heart of his Caribbean empire.
Reprinted courtesy of
Jim Wyss, Bloomberg and
Tom Maloney, Bloomberg Read the full story...
Penalty for Failure to Release Expired Liens
April 02, 2024 —
William L. Porter - Porter Law GroupI was recently contacted by a commercial building owner in the process of trying to sell his building. Two years prior to this, a subcontractor had recorded a mechanics’ lien with the local County Recorder’s office in relation to the owner’s property. The subcontractor recorded the mechanics lien after the subcontractor was not paid by a prime contractor for work the subcontractor had performed on the property. Unfortunately, the subcontractor then failed to file a lawsuit to foreclose on the lien within the requisite ninety (90) day time period for filing a lawsuit to foreclose on the mechanics’ lien. Since the subcontractor missed this 90 day deadline to file the mechanics lien foreclosure lawsuit, the mechanics lien expired and became unenforceable.
Subject to certain exceptions, under California Civil Code Section 8460, a lawsuit to foreclose on a mechanics lien must be filed within ninety (90) days after the mechanics lien is recorded or the mechanics lien expires. Although the mechanics lien had expired, the title company and intended purchaser of the building and property were perhaps understandably insistent that the mechanics lien constituted a cloud on title to the property and must be removed from the official records for the property. The prospective purchaser would not buy the property unless the mechanics’ lien was removed.
Read the full story...Reprinted courtesy of
William L. Porter, Porter Law GroupMr. Porter may be contacted at
bporter@porterlaw.com
2024 Construction Law Update
December 23, 2023 —
Garret Murai - California Construction Law BlogWe would like to wish you and yours a happy holiday season as we approach 2024.
The first half of the 2023-2024 legislative session saw the introduction of 3,028 bills, which, according to legislative observers, are the most bills introduced in a session in more than a decade, perhaps reflecting the fact that California has a record number of new legislators with over a quarter taking the oath of office for the first time. Of these bills, Governor Newsom signed nearly 400 into law including several impacting the construction industry related to climate change and housing affordability.
Read the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
Navigating the Construction Burrito: OCIP Policies in California’s Construction Defect Cases
November 16, 2023 —
Alexa Stephenson & Ivette Kincaid - Kahana FeldIn the early 2000’s, Owner-Controlled Insurance Programs (OCIP) or WRAPS, were traditionally used in large commercial projects of over $50 million in construction costs. As construction defect lawsuits became more prevalent, subcontractors found themselves unable to meet the insurance requirements of their contracts with developers and general contractors because they could not find insurance companies that were willing to insure the risk. This presented a problem for developers and general contractors and left them with no option but to look into new insurance products that would insure them and all subcontractors who worked on the project. OCIPs became in some instances the only insurance option for developers, general contractors, and subcontractors to build single-family or multi-family projects in California and other western states.
OCIPS or WRAPS, often likened to the layers of a savory burrito, offer both enticing benefits and potential pitfalls. Just as a burrito’s ingredients can harmonize or clash, OCIP policies can shape the outcome of legal battles, impacting contractors, developers, and insurers alike.
Pros – Savoring the OCIP Burrito:
1. Wrapped Protection: Much like a well-folded burrito envelops its contents, OCIP policies offer comprehensive coverage for construction projects. Developers, general contractors, and subcontractors find comfort in knowing that their liability risks are bundled into a single policy, ensuring all enrolled parties have coverage in the event of a claim.
Reprinted courtesy of
Alexa Stephenson, Kahana Feld and
Ivette Kincaid, Kahana Feld
Ms. Stephenson may be contacted at astephenson@kahanafeld.com
Ms. Kincaid may be contacted at ikincaid@kahanafeld.com
Read the full story...