Top Developments March 2024
April 22, 2024 —
Complex Insurance Coverage ReporterCLAIMS-MADE COVERAGE
Zurich Am. Ins. Co. v. Syngenta Crop Prot. LLC, 2024 Del. LEXIS 68 (Del. Feb. 26, 2024)
Delaware Supreme Court concludes that a letter from a lawyer informing an insured of possible lawsuits without identifying potential plaintiffs or demanding payment is not a “claim for damages” within the meaning of claims-made CGL and umbrella liability policies. Citing case law from Delaware and other jurisdictions, it reasoned that, in the ordinary sense, a “claim for damages” (which the policies did not define) is “a demand or request for monetary relief by or on behalf of an identifiable claimant.” According to the court, the letter in question did not meet this definition because it did not identify any claimants “except in the vaguest terms” or request monetary relief on any claimant’s behalf, but rather communicated only a threat of future litigation. As a result, the letter was not a claim made before the policy periods at issue.
POLLUTION EXCLUSION
Wesco Ins. Co. v. Brad Ingram Constr., 2024 U.S. App. LEXIS 1488 (9th Cir. Jan. 23, 2024)
A divided Ninth Circuit panel, applying California law, holds that a pollution exclusion* in a CGL policy does not preclude a duty to defend an underlying suit alleging physical injury from exposure to “clouds of toxic dust” deposited in the environment by a wildfire and released during clean up efforts. Citing MacKinnon v. Truck Ins. Exch., 73 P.3d 1205 (Cal. 2003), the majority explained that determining whether a “pollution event” (i.e., “environmental pollution”) resulting in excluded injury has occurred involves consideration of “the character of the injurious substance” and whether the exposure resulted from a “mechanism specified in the policy.” It concluded that a potential for coverage (and, therefore, a defense obligation) existed because, although wildfire debris may be considered a “pollutant” in certain circumstances, the mechanism alleged in the underlying complaint – “expos[ure] . . . to clouds of toxic dust during the loading and unloading of [the underlying plaintiff’s] truck” – did not clearly constitute an “event commonly thought of as pollution.”
Read the full story...Reprinted courtesy of
White and Williams LLP
Round and Round: Inside the Las Vegas Sphere
December 16, 2023 —
Grace Calengor - Construction ExecutiveHow does the typical contractor approach building something taller than the Statue of Liberty, wider than a football field and with the most square footage of LED lighting in the world? Perhaps it’s enough to say that Sphere Entertainment Company is not your average contractor—and Sphere in Las Vegas is not your average construction project.
With a budget of approximately $2.3 billion, Sphere is a massive entertainment venue constructed mainly of steel and concrete. How different is that from the typical Vegas high-rise, casino or hotel? When you account for the structure’s sheer size, uncommon shape and intertwining technologies—very.
Reprinted courtesy of
Grace Calengor, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the full story...
Maui Wildfire Cleanup Advances to Debris Removal Phase
February 05, 2024 —
James Leggate - Engineering News-RecordContractors hauled the first truckload of debris from homes destroyed by last year’s wildfires in Lahaina, Hawaii, on Jan. 16. The move marked the beginning of the second phase of debris removal efforts coordinated by federal, state and local officials.
Reprinted courtesy of
James Leggate, Engineering News-Record
Mr. Leggate may be contacted at leggatej@enr.com
Read the full story...
Real Estate & Construction News Roundup (3/20/24) – Construction Backlog Falls, National Association of Realtors Settle Litigation, and Commercial Real Estate Market’s Effect on City Cuts
April 15, 2024 —
Pillsbury's Construction & Real Estate Law Team - Gravel2Gavel Construction & Real Estate Law BlogIn our latest roundup, bad loans outweigh loss reserves at top six U.S. banks, the FCC announces a proposed rule aimed at “bulk billing,” office-to-multifamily conversion projects grow in major metro cities, and more!
- The National Association of Realtors has agreed to settle litigation that accused them of artificially inflating real estate commissions – a major decision that could reshape the housing market for buyers, sellers and agents. (Rachel Siegel, The Washington Post)
- An NYU professor considers the positives and negatives of cities cutting services or raising other kinds of taxes to offset the continued faltering of the commercial real estate market. (Alan Rappeport, The New York Times)
- Construction backlog fell in February for every size of contractor except for those with under $30 million in annual revenue, while, over the past year, the largest contractors – those with greater than $50 million in revenue – have experienced the greatest decline in backlog. (Sebastian Obando, Construction Dive).
Read the full story...Reprinted courtesy of
Pillsbury's Construction & Real Estate Law Team
Enforceability of Contract Provisions Extending Liquidated Damages Beyond Substantial Completion
April 15, 2024 —
Stu Richeson - The Dispute ResolverThis post takes a look at the enforceability of contract provisions providing for liquidated delay damages after substantial completion. Typically, the assessment of liquidated delay damages ends at substantial completion of a project. However, various standard form contracts, including some of the ConsensusDocs and EJCDC contracts, contain elections allowing for the parties to agree on the use of liquidated damages for failing to achieve substantial completion, final completion, or project milestones. The standard language in the AIA A201 leaves it up to the parties to define the circumstances under which liquidated damages will be awarded.
Courts are split on the enforceability of provisions that seek to assess liquidated damages beyond substantial completions. Courts in some jurisdictions will not impose liquidated damages after the date of substantial completion on the ground that liquidated damages would otherwise become a penalty if assessed after the owner has put the project to its intended use. Perini Corp. v. Greate Bay Hotel & Casino, Inc., 129 N.J. 479, 610 A.2d 364 (1992). When the terms are clear, other jurisdictions will enforce contract terms providing for liquidated damages until final completion, even if the owner has taken beneficial use of the facility. Carrothers Const. Co. v. City of S. Hutchinson, 288 Kan. 743, 207 P.3d 231 (2009).
Read the full story...Reprinted courtesy of
Stu Richeson, PhelpsMr. Richeson may be contacted at
stuart.richeson@phelps.com
Best Practices: Commercial Lockouts in Arizona
March 19, 2024 —
Patrick Tighe - Snell & Wilmer Real Estate Litigation BlogIf a tenant defaults under a commercial lease, Arizona law permits the landlord to re-take possession of the premises by locking out the defaulting tenant. However, if the landlord’s lockout is wrongful, the landlord may be liable for the damages the tenant sustains because of the wrongful lockout. To minimize such liability, here are some general best practices to follow when locking out a defaulting tenant:
- Do Not Breach the Peace. It is vital when performing a lockout to not breach the peace. What constitutes a “breach of the peace” depends on the particular circumstances at hand. For example, if a tenant arrives during the lockout and becomes angry or threatens violence, the landlord should stop performing the lockout and return at a later time. As a general rule of thumb, it is best to perform lockouts in the early morning hours or in the late evening hours when the landlord is less likely to encounter the tenant.
- Provide A Notice of Default. Many commercial leases require the landlord to provide a notice of default before the landlord can lock out a defaulting tenant. Check, double check, and triple check that the landlord followed the lease’s notice of default provisions correctly, including that the landlord sent the notices to all required parties in accordance with the time requirements set forth in the lease.
Read the full story...Reprinted courtesy of
Patrick Tighe, Snell & WilmerMr. Tighe may be contacted at
ptighe@swlaw.com
A Brief Primer on Perfecting Your Mechanics Lien When the Property Owner Files Bankruptcy
January 22, 2024 —
William L. Porter - Porter Law GroupOverview of the Mechanics Lien Law
This is a brief description of steps to be taken when the Owner of property on which you have recorded a mechanics lien files bankruptcy.
The California mechanics lien is a powerful tool for contractors, subcontractors and materials suppliers to secure payment of unpaid construction debts. A contractor, subcontractor or materials supplier is allowed to record a mechanics lien on real property, based on the value added to the property by the claimant during the construction process.
The recorded mechanics lien provides the claimant with legal right to force the sale of the improved real property and thereby obtain the funds necessary to pay the delinquent debt. Under the usual procedure, the first step is the recording of the mechanics lien with County Recorder’s office in the County where the property is located. A lawsuit to foreclose on the lien must then be filed in the County Superior Court of that County, within ninety (90) days after the mechanics lien is recorded. The goal of the lawsuit is to obtain a judgment for foreclosure on the mechanics lien in order to force a sale of the property. The net proceeds of the sale will be used to pay the unpaid construction debt secured by the recorded mechanics lien, assuming sale proceeds exceed the amount of senior liens and encumbrances.
Read the full story...Reprinted courtesy of
William L. Porter, Porter Law GroupMr. Porter may be contacted at
bporter@porterlaw.com
Navigating Threshold Arbitration Issues in Construction Contracts
April 29, 2024 —
Daniel D. McMillan and TJ Auner - The Dispute ResolverIncluding an arbitration clause in your construction contract may not mean that your dispute will be confined to arbitration. Instead, parties often find themselves in court litigating threshold issues related to the existence and/or enforceability of an arbitration clause. Common issues include whether the underlying contract containing the arbitration clause is valid, whether the dispute falls within the scope of the clause, whether the parties complied with contractual prerequisites to arbitration, whether issues related to arbitrability are decided by the court or arbitrator, and whether one of the parties has waived their right to arbitrate. This blog post highlights two recent construction cases addressing threshold issues that a party seeking to enforce—or oppose enforcing—an arbitration clause might face.
Seifert v. United Built Homes, LLC: Delegating Issues of Arbitrability to the Arbitrator
In Seifert, an owner sued a homebuilder in Texas federal court for breach of contract and sought damages and declaratory relief. No. 3:22-CV-1360-E, 2023 WL 4826206 (N.D. Tex. July 27, 2023). The builder moved to compel arbitration. The owner opposed and argued that: (1) there was no agreement to arbitrate because the underlying contract was null and void, and (2) its claim for declaratory relief fell outside the scope of the arbitration clause. The court did not address the merits of either argument. Instead, it determined that these were issues for the arbitrator to decide.
Reprinted courtesy of
Daniel D. McMillan, Jones Day and
TJ Auner, Jones Day
Mr. McMillan may be contacted at ddmcmillan@jonesday.com
Mr. Auner may be contacted at tauner@jonesday.com
Read the full story...