Don’t Ignore a Notice of Contest of Lien
April 29, 2024 —
David Adelstein - Florida Construction Legal UpdatesA recent case, Jon M. Hall Company, LLC v. Canoe Creek Investments, LLC, 49 Fla.L.Weekly D812a (Fla. 2d DCA 2024), demonstrates four important things when it comes to liens:
- An owner can shorten the time period to foreclose on the lien, whether against the real property or a lien transfer bond, to 60 days by recording a notice of contest of lien;
- An owner can transfer a lien to a lien transfer bond during litigation;
- An owner can record a notice of contest of lien to force the lienor to amend its lawsuit to sue the lien transfer bond surety within 60 days; and
- A contractors’ failure to amend its lawsuit to sue the lien transfer bond within 60 days will extinguish its rights to pursue a claim against the lien transfer bond, and will otherwise extinguish the lien, fairly or unfairly.
Read the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
'Taylor Swift Is an Economic Phenomenon': CE's Q1 2024 Economic Update and Forecast
April 29, 2024 —
Grace Calengor - Construction ExecutiveOn March 27, Construction Executive presented its "2024 Q1 Economic Update and Forecast," hosted by ABC Chief Economist Anirban Basu. If you've attended previous versions of this webinar, you're familiar with Basu’s pragmatic approach to the economics of the construction industry and his penchant for predicting recession. But this quarter, he opted for an almost-optimistic approach and hinted at walking back his thoughts on recession. Read the most quotable moments, new poll results and top takeaways from the presentation below.
POLL RESULTS: Q1 2024 vs. Q4 2023 Poll 1: Which of these is the leading challenge for your company today?
Supply chain and/or materials issues
Skills/worker shortage
Insufficient demand for construction services
Availability of financing for projects/project work
None of the above
December 2023 | March 2024 |
10% |
7% |
57% |
60% |
11% |
11% |
19% |
17% |
3% |
6% |
Reprinted courtesy of Grace Calengor, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Build, Baby, Build. But Not Like This, Britain.
March 04, 2024 —
Matthew Brooker - BloombergThe UK needs to do a lot more building. A lack of access to physical and digital connections is holding back the economy, the government says. Besides tackling the housing crisis, the country has to construct more roads, railways, wind farms and reservoirs to open up opportunity and drive productivity. The only problem is that Britain is notoriously inept at delivering infrastructure projects on time and within budget.
The advantage of doing things badly is that at least you get to learn from your mistakes — in theory. Updates this month have offered some illuminating insights into two of the biggest civil-engineering undertakings in the country: High-Speed Rail 2, better known as HS2, and Hinkley Point C, which will be Britain’s first new nuclear power station since 1995. Here are five lessons that can be drawn from the issues encountered by two projects with a combined bill that’s likely to exceed £100 billion ($127 billion):
Don't take budgets too seriously — especially at the start. Fixing an initial budget that was too low may have done much to feed later perceptions that HS2’s costs were spiraling out of control. The original estimate for the expanded train network was set too early and based on “very immature data,” Jon Thompson, appointed executive chair of High Speed 2 Ltd. in February last year, told the House of Commons transport committee. Numbers get more accurate and reliable as work progresses and the quality of information improves. What were viewed as cost blowouts partly reflected this process. The effect was unfortunate, undermining political support for HS2 and providing cover for cutbacks that have reduced the network to a single line between London and Birmingham that fails to fulfill most of its original purpose. To avoid this problem: Stick to a range rather than a single figure, and make sure people understand the uncertainties inherent in early-stage estimates.
Read the full story...Reprinted courtesy of
Matthew Brooker, Bloomberg
Ruling Dealing with Constructive Changes, Constructive Suspension, and the Implied Covenant of Good Faith and Fair Dealing
January 22, 2024 —
David Adelstein - Florida Construction Legal UpdatesA dispute pending in the Armed Services Board of Contract Appeals (ASBCA) dealt with interesting legal issues on a motion to dismiss. See Appeals of McCarthy Hitt-Next NGA West JV, ASBCA No. 63571, 2023 WL 9179193 (ASBCA 2023). The dispute involves a contractor passing through subcontractor claims due to impacts caused by the COVID-19 pandemic and the government’s response to the pandemic. More particularly, the claim centers on the premise that the government “failed to work with [the contractor] in good faith to develop a collaborative and cooperative approach to manage and mitigate the impacts and delays arising from the COVID-19 pandemic.” See Appeals of McCarthy Hitt.
The contractor (again, submitting pass through claims from subcontractors) claimed: (a) constructive changes to the contract entitling it to an equitable adjustment under the Changes clause of Federal Acquisition Regulation (F.A.R.) 52.243-4; (b) construction suspensions of the contractor’s work entitling it to an equitable adjustment under the Suspensions of Work clause of F.A.R. 52-242-14; and (c) the government breached the implied covenant of good faith and fair dealing. Each of these legal issues and theories will be discussed below because they are need-to-know legal issues. Keep these legal issues in mind, and the ASBCA’s ruling on the motion to dismiss as its analysis may demonstrate fruitful in other applications.
Read the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Washington’s Court of Appeals Protects Contracting Parties’ Rights to Define the Terms of their Indemnity Agreements
March 19, 2024 —
Margarita Kutsin - Ahlers Cressman & Sleight PLLCIt has long been the law in Washington that contracting parties are free to draft contractual indemnity agreements to allocate risk arising from performance of the work, and Courts will generally enforce those agreements as written. This well-settled principle was recently reaffirmed in King County v. CPM Development Corp., dba ICON Materials[1] a decision from Division I of the Washington Court of Appeals, wherein one party to an indemnity agreement attempted to evade its contractual obligations by arguing that certain common law indemnity principles supersede the written terms. This appeal followed a multi-week jury trial from which the client and Ahlers Cressman and Sleight legal team, including Lindsay Watkins, Klien Hilliard, and Christina Granquist, obtained a seven-figure judgment in the client’s favor, including an award of all attorneys’ fees and costs.
ICON was the general contractor on a Vashon Island Highway Pavement project for King County. Part of the work on the project involved hauling away and disposing of ground milled asphalt (the “millings”) at King County-approved sites. ICON and D&R Excavating Inc., (“D&R”) executed a subcontract for D&R to perform that work. The subcontract incorporated the contract between ICON and King County, including the obligation to stockpile millings only at approved sites. D&R, however, did not obtain the requisite approvals from King County, and placed the millings at various sites on the Island, including locations that King County explicitly rejected.
Read the full story...Reprinted courtesy of
Margarita Kutsin, Ahlers Cressman & Sleight PLLCMs. Kutsin may be contacted at
margarita.kutsin@acslawyers.com
Top 10 Take-Aways: the ABA Forum's 2024 Mid-Winter Meeting
February 26, 2024 —
Marissa L. Downs - The Dispute ResolverThe Forum on Construction Law convened last week at Caesars Palace in sunny Las Vegas for its 2024 Mid-Winter Meeting. Carrie Okizaki and David Suchar (along with John Cook, Karen Erger, and countless others) put together a truly outstanding program on power projects. Here are my top 10 take-aways from this unique and insightful event:
10. The demand for power projects is steadily increasing. The increasing demand for power construction projects is being driven chiefly by the need to replace aging infrastructure as well as the desire to develop cleaner and more sustainable generation facilities. The constant demand for more and more electricity is not that surprising but, according to Jeff Richardson (Energy Solutions) and Eric S. Gould (Modus Strategic Solutions), the pipeline market size for power-generation projects in 2028 is expected to reach $10.6 trillion, i.e., double what it was just in 2022.
9. "Net Zero" is the new normal. In December 2021, President Biden issued an executive order proclaiming that, by 2050, the federal government will be a Net-Zero contributor to the climate crisis. To achieve this goal, the greenhouse gasses ("GHGs") released by government operations must be less than (or equal to) the GHGs absorbed/removed from the environment. Other government bodies and private companies alike are adopting similar Net-Zero goals. Because not all of these promises are created equal, Moody’s Investors Services has a tool to help consumers compare and evaluate companies' carbon transition plans. According to panelists, Amanda Schermer MacVey (Venable), Brendan Hennessey (Pillsbury), and Laszlo von Lazar (Black & Veatch), these Net-Zero commitments are likely to result in more rigorous supplier codes of conduct and heightened carbon tracing efforts on construction projects.
Read the full story...Reprinted courtesy of
Marissa L. Downs, Laurie & Brennan, LLPMs. Downs may be contacted at
mdowns@lauriebrennan.com
Appellate Court Lacks Jurisdiction Over Order Compelling Appraisal
January 16, 2024 —
Tred R. Eyerly - Insurance Law HawaiiThe Eleventh Circuit recently held that the district court's order compelling appraisal and staying the proceedings pending appraisal was an interlocutory order that was not immediately appealable under 28 U.S.C. 1292 (a) (1). Positano Place at Naples Condominium Association, Inc. v. Empire Indem. Ins. Co., 2023 U.S. App. LEXIS 27961 (11th Cir. Oct. 20, 2023).
Postiano Condominium Association suffered damage from Hurricane Irma. Pastiano notified its insurer, Empire, seven months later. Empire investigated the claim and inspected the property. Positano sent a written request for appraisal. Empire did not respond and Pastiano filed suit, alleging that the parties' dispute was not a coverage dispute but a dispute over the amount of the loss. Postiano moved to compel appraisal and to stay the proceedings pending completion of the appraisal.
Read the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Victoria Kajo Named One of KNOW Women's 100 Women to KNOW in America for 2024
May 13, 2024 —
Lewis Brisbois NewsroomLos Angeles, Calif. (April 30, 2024) – Los Angeles Partner Victoria Kajo has been named to global media company KNOW Women's 2024 100 Women to KNOW in America list, which honors the top 100 female leaders across North America. The honorees were recognized at the annual KNOW Women Summit, held from April 21-23 at The Palomar Hotel in Phoenix, Arizona.
The annual 100 Women to KNOW in America award, presented by JPMorgan Chase, recognizes women entrepreneurs, executives, creatives, and philanthropists who "exemplify what it means to be high achieving and ambitious on the next level and who continue to pour into their communities as they do so," according to KNOW Women. Ms. Kajo was selected as one of this year's honorees following a nomination and interview process.
Ms. Kajo is a member of Lewis Brisbois' Professional Liability Practice. She has extensive experience with professional liability litigation, having defended lawyers, design professionals and real estate professionals against claims of alleged negligent acts and omissions in the performance of their professional services. Ms. Kajo also has broad experience in general civil litigation matters involving errors and omissions, real estate, wrongful foreclosures, labor and employment law, civil rights, fraud, personal injury, breach of contract and unlawful detainer matters, amongst others.
Read the full story...Reprinted courtesy of
Lewis Brisbois